Hire request checklist
Write a hire request suppliers can quote properly
Eight blocks that turn “I need a 20-tonner” into a scope every supplier prices the same way. Quotes become comparable, and the hire runs with fewer surprises.
8 blocks
The complete hire specification
Copy these headings into your request for quote. Mark anything unknown as “supplier to confirm” so it is priced openly instead of hidden in a total.
Duty
What the machine must achieve.
- Task and material
- Quantity and production target
- Maximum reach, depth or lift
- Required finish or tolerance
Geometry & site
Where the machine must fit and work.
- Gate and access width
- Overhead and underground services
- Ground bearing and slope
- Exclusion zones and swing space
Machine
What the supplier should nominate.
- Make/model or equivalent
- Operating mass and capacity
- Configuration and safety systems
- Emissions or noise limits
Attachments
The tools that do the work.
- Buckets, breakers, forks, jibs
- Hitch/coupler compatibility
- Hydraulic flow and pressure
- Machine control
People
Who operates and supervises.
- Wet or dry hire
- Licences and competencies
- Site inductions
- Shift pattern and fatigue
Movement
Getting to and from site.
- Dispatch depot
- Transport dimensions and mass
- Permits and escorts
- Unloading area and delivery window
Support
Keeping the machine working.
- Fuel and servicing
- Breakdown response time
- Replacement threshold
- After-hours contact
Commercial
How the hire is charged.
- Rate basis and minimum hire
- Included hours and overtime
- Standby and wet weather
- Damage waiver, cleaning and off-hire
FAQFrequently asked questions
Why do machinery hire quotes vary so much?
Suppliers often price different assumptions: minimum hours, operator, attachments, transport, fuel and standby. A complete specification means every supplier prices the same scope.
Should I specify a brand or model?
Specify the performance you need (reach, capacity, dimensions) and ask the supplier to nominate the make and model. Name a model only when a specific configuration is essential.
What if I don't know some of the inputs?
Mark them “supplier to confirm” and ask for the assumption to be stated in the quote. Hidden assumptions cause most variations.