
Planning tool · Shift planner
How many usable hours per shift?
Paid hours are not productive hours. Subtract pre-starts, breaks and refuelling to find the machine window you can actually plan production on.
Planned machine window
8.0 usable hours
80% of the rostered shift, before access delays, waiting on trucks, attachment changes, breakdowns or weather.
Base production estimates on the usable window, not the roster length. If you pay for 10 hours but plan on 10 hours of output, the programme is already behind.
Useful utilisation guideHow to use itUsing the shift planner
- Enter the rostered shift length the machine is hired for.
- Add realistic allowances for pre-start, breaks and refuelling from your site rules.
- Multiply usable hours by the measured production rate to estimate output per shift.
- Record actual delays for a week and update the allowances.
FAQFrequently asked questions
What is a realistic utilisation for hired plant?
It varies with the task and site organisation. Measure it: compare paid hours, engine hours and productive hours for your own site rather than relying on a general figure.
Are breaks and pre-starts charged in wet hire?
Usually yes. The machine and operator are on hire for the whole shift. That is why planning production on the usable window matters.